Kolkata Metro Line 1

The Line 1, also known as North–South Metro of the Kolkata Metro, is a rapid transit system serving Kolkata and North 24 Parganas in Indian state of West Bengal. It consists of 24 operational stations from Kavi Subhash to Noapara, of which 7 are elevated, 2 are at grade and the remaining 15 are underground and 2 other elevated stations under construction with a total distance of 31 km. The line connects Noapara and New Garia and uses 5 ft 6 in (1,676 mm) Broad gauge rolling stock. Noapara was opened on 10 July 2013 and is elevated and is located 2.09 km. north of Dum Dum. It was the first underground railway to be built in India, with the first operations commencing in October 1984 and the full stretch that was initially planned being operational by February 1995. On 28 December 2010, it became the 17th zone of the Indian Railways.[2] Being the country's first, and a completely indigenous process, the construction of the Kolkata Metro was more of a trial-and-error affair, in contrast to the Delhi Metro, which has seen the involvement of numerous international consultants. As a result, it took nearly 23 years to completely construct around 15 km underground railway from Birpara up to Tollygunge Metro Station.

Kolkata Metro Line 1

North–South Metro
Overview
StatusOperational
OwnerMetro Railway, Kolkata
Locale Kolkata Metropolitan Area, India
TerminiKavi Subhash (south)
Noapara (north) with an extension to Dakshineswar (north)
Connecting lines Line 2   Line 3   Line 4   Line 5   Line 6 
Stations26 (24 operational)
Websitehttps://mtp.indianrailways.gov.in
Service
TypeRapid transit
SystemKolkata Metro
Operator(s)Metro Railway, Kolkata Indian Railways
Depot(s)Noapara, Tollygunge and New Garia
Rolling stockIntegral Coach Factory (ICF) and CRRC Dalian
Daily ridership700,000 to 750,000 (Weekdays)
Ridership380,000 (Weekends)
History
Opened24 October 1984 (1984-10-24)
Last extensionNoapara (2013)
Technical
Line length31.365 kilometres (19.489 mi) (27.28 km operational)[1]
Number of tracks2
Character
  • Surface – 2
  • Underground – 15
  • Elevated – 9
Track gauge1,676 mm (5 ft 6 in) Broad gauge
Electrification750 V DC using Third rail
Operating speed55 km/h (in service)
SignallingIndian Railways signalling system
Route map

Dakshineswar
Baranagar
Noapara
Keshtopur Canal
Dum Dum
Belgachia
Circular Canal
Shyambazar
Shobhabazar Sutanuti
Girish Park
Mahatma Gandhi Road
Central
Chandni Chowk
 Line 2 
← to Howrah Maidan
to Teghoria
Esplanade
Park Street
Maidan
Rabindra Sadan
Netaji Bhavan
Jatin Das Park
Kalighat
Tollygunge
Rabindra Sarobar
Mahanayak Uttam Kumar
Netaji
Masterda Surya Sen
Gitanjali
Kavi Nazrul
Shahid Khudiram
Kavi Subhash

History

The laying of the founding stone was done in 1972, but actual construction of line 1 started only in 1978. Line 1 is 27.28 km long with 24 stations (see above). Running of the first metro car on the line by 1984 was considered a great engineering challenge. Former railways minister A. B. A. Ghani Khan Chowdhury took a massive effort to perform it. The first section opened between Esplanade & Bhawanipore (now called Netaji Bhawan). First day Metro Railway Kolkata was started by Sri Tapan Kumar Nath and Sri Sanjay Sil. There were no connections of this stretch with the two depots at Dum Dum & Tollygunge (Now called Mahanayak Uttam Kumar). So metro cars had to be put down on the track near Esplanade by crane, by directly digging the road surface. Initially, only four-car trains were run until 1986. There were no magnetic gates or escalators at that time and ordinary revolving gates served as exits. The Metro too operated on only a single line. Two years later, line 1 extended up to Tollygunge, at the southern end. At the same time, the metro service was extended to the double line. Magnetic tickets and more entry gates were also introduced at that time. The number of compartments in each train was increased to eight.

Metro service was also started from Dum Dum, at the northern end, to Belgachia in parallel with the extension of the line to the south. But this short portion was not popular and the service was closed down to be restarted when the entire stretch along the north-south corridor was completed.

After 1986 many political incidents hampered the construction, and work almost stopped for nearly six years. After restarting work, the Dum Dum to Shyambazar metro service was started in 1994. This portion was served by four-car trains. Two months later, the Esplanade – Chandni Chowk section was opened and Chandni Chowk – Central section opened three months later. The service from Dum Dum to Tollygunge started in 1995, with Mahatma Gandhi Road metro station, opening in 1996. During this time, more magnetic gates and escalators were added and the revolving gates were slowly phased out.

In 2009, a large number of stations on Line 1 were renamed by then Minister of Railways Mamata Banerjee.[3]

Timeline

The following dates represent the dates the section opened to the public, not the private inauguration.

History
Extension date Terminals Length
24 October 1984EsplanadeBhowanipore3.40 kilometers (2.11 mi)
12 November 1984Dum DumBelgachhia2.15 kilometers (1.34 mi)
29 April 1986Bhowanipur (now Netaji Bhaban)Tollygunge (now Mahanayak Uttam Kumar)4.24 kilometers (2.63 mi)
13 August 1994BelgachhiaShyambazar1.63 kilometers (1.01 mi)
2 October 1994EsplanadeChandni Chowk0.71 kilometers (0.44 mi)
19 February 1995ShyambazarGirish Park1.92 kilometers (1.19 mi)
19 February 1995Chandni ChowkCentral0.60 kilometers (0.37 mi)
27 September 1995CentralGirish Park1.80 kilometers (1.12 mi)
22 August 2009Tollygunge (Mahanayak Uttam Kumar)Garia Bazar (now Kavi Nazrul)5.85 kilometers (3.64 mi)
7 October 2010Garia Bazar (now Kavi Nazrul)New Garia (now Kavi Subhash)3.00 kilometers (1.86 mi)
10 July 2013Dum DumNoapara2.09 kilometers (1.30 mi)
TotalNoaparaNew Garia (now Kavi Subhash)27.39 kilometers (17.02 mi)

List of stations (North to South)

The stations of this Corridors are:

Line 1 (North-South Corridor)
No. Station Name Location Phase Opening Connections Layout Platform Type Depot Coordinates Notes
EnglishBengali
1Dakshineswarদক্ষিণেশ্বরDakshineswar 7Under construction Dakshineswar

Dakshineswar Bus Stand

Alambazar More bus Stop

Ma Bhabotarini Jetty Ghat

Elevated Side  
2BaranagarবরাহনগরBaranagarUnder construction Line 1  (Under construction)

 Line 5  (Planned)

Baranagar Road

Dunlop Bus Stand

Elevated22°37′23″N 88°25′38″EAlso known as Dunlop Crossing[4]
3Noaparaনোয়াপাড়াNoapara 610 July 2013 Line 4  (Under Construction)

34C Bus Stand

Health More Bus Stop

Gharui Paschimpara Bus Stop

Elevated Both side & island Noapara depot22°38′23″N 88°23′38″E
4Dum DumদমদমDum Dum 1B12 November 1984 Dum Dum Jn

Dum Dum Station Bus Stop

Elevated Side  
5Belgachhiaবেলগাছিয়াBelgachia12 November 1984

Belgachia Tram Depot

Belgachia Bus Depot

Belgachia Metro Bus Stop

Belgachia More Bus Stop

Underground Island
6Shyambazaarশ্যামবাজারShyambazar 3A15 February 1995

Shyambazar Tram Depot

Shyambazar Metro Bus Stop

Shyambazar 5 Point Bus Stop

Shyambazar Bus Stand

Underground Island
7Shobhabazar Sutanutiশোভাবাজার সুতানুটিShobhabazar15 February 1995

Shobhabazar Metro Bus Stop

Jaipuria College Bus Stop

Underground Island
8Girish Parkগিরিশ পার্কJorasanko15 February 1995 Girish Park Bus Stop Underground IslandAlso known as Jorasanko
9Mahatma Gandhi Roadমহাত্মা গান্ধী রোডBurrabazar 3B27 September 1995 Mahajati Sadan Bus Stop

Ram Mandir Bus Stop

Muhammad Ali Park Bus Stop

Muhammad Ali Park Tram Stop

Underground IslandAlso known as Mahajati Sadan
10Centralসেন্ট্রালBoubazar 3A15 February 1995

Central Avenue Bus Stop

Central Metro Station Bus Stop

School of Tropical Medicine Bus Stop

Medical College Bus Stop

Underground Both side & islandAlso known as Bowbazar
11Chandni Chowkচাঁদনি চকChandni Chowk15 February 1995

Chandni Chowk Bus Stop

Victoria House Bus Stop

Underground Island
12Esplanadeএসপ্ল্যানেডDharmatala 1A24 October 1984 Line 2  (Under Construction)

 Line 3  (Under Construction)

Esplanade Tram Depot

Esplanade Bus Station(WBTC,CTC,SBSTC,NBSTC)

Underground IslandInternational Bus Terminus. Also known as Dharmatala / Chowringhee
13 Park Street পার্ক স্ট্রীট Park Street 24 October 1984  Line 3  (Under Construction)

Park Street Bus Stop

Underground Side Now Mother Teresa Sarani
14 Maidan ময়দান Maidan 24 October 1984 Maidan Bus Stop Underground Island
15 Rabindra Sadan রবীন্দ্র সদন Rabindra Sadan 24 October 1984 Exide More Bus Stop

Rabindra Sadan Bus Stop

Chowringhee Road-Calcutta Club Bus Stop

Underground Island Also known as Exide
16 Netaji Bhavan নেতাজি ভবন Bhawanipore 24 October 1984 Netaji Bhawan Bus Stop

Jadu Babur Bazar Bus Stop

Underground Island Also known as Bhawanipore
17 Jatin Das Park যতীন দাস পার্ক Hazra 2 29 April 1986 Hazra Bus Stop

Jatin Das Park Bus Stop

Sujata Sadan Bus Stop

Underground Island Also known as Hazra
18 Kalighat কালীঘাট Kalighat 29 April 1986 Rasbehari Crossing Tram Stop

Rashbehari Crossing Bus Stop

Rashbehari Gurudwara Bus Stop

Underground Island Also known as Rashbehari
19 Rabindra Sarobar রবীন্দ্র সরোবর Rabindra Sarobar 29 April 1986 Tollygunge

Charu Market Tram Stop

Rabindra Sarobar Bus Stop

Bhabani Cinema Bus Stop

Underground Island Also known as Charu Market
20 Mahanayak Uttam Kumar মহানায়ক উত্তমকুমার Tollygunge 29 April 1986 Tollygunge Tram Depot

Tollygunge Bus Depot

Tollygunge Tram Depot Bus Stop

At Grade Both side & island Tollygunge depot Also known as Tollygunge
21 Netaji নেতাজি Kudghat 4 22 August 2009 Kudghat Bus Stand Elevated Side   Also known as Kudghat
22 Masterda Surya Sen মাস্টারদা সূর্য সেন Bansdroni 22 August 2009 Bansdroni Bus Stand Elevated Side Also known as Bansdroni
23 Gitanjali গীতাঞ্জলি Naktala 22 August 2009 Rathtala Bus Stop

Naktala Minibus Stand

Bunty Cinema Bus Stop

Elevated Side Also known as Naktala
24 Kavi Nazrul কবি নজরুল Garia 22 August 2009 Garia Metro Bus Stop

Garia More Bus Stop

Garia Bazar Bus Stop

Garia 6 Number Bus Stand

Garia 5 Number Bus Stand

Elevated Side Also known as Garia Bazar
25 Shahid Khudiram শহিদ ক্ষুদিরাম Briji 5 7 October 2010 Khudiram Metro Bus Stop

Dhalai Bridge Bus Stop

Elevated Side Also known as Dhalai Bridge
26 Kavi Subhash কবি সুভাষ New Garia 7 October 2010  Line 6  (Under Construction)

New Garia

New Garia Bus Stand

At Grade Side New Garia depot Also known as New Garia
Kolkata Metro near Dum Dum metro station

Alignment & interchanges

Dum Dum, Park Street, Mahanayak Uttam Kumar, Netaji, Masterda Surya Sen, Gitanjali, Kavi Nazrul, Shahid Khudiram and Kavi Subhash have side platforms; all other stations have island platforms. Central and Noapara are exceptions as they have both platforms on the sides as well as in the centre. Dum Dum, Kavi Subhash and Rabindra Sarobar have connections to interchange with Kolkata Suburban Railway. Shyambazar, Mahatma Gandhi Road, Esplanade, Kalighat, Rabindra Sarobar & Mahanayak Uttam Kumar stations have connections to the tram network. EM Bypass can be accessed from the Shahid Khudiram metro station and Kavi Subhash metro station.

Extension up to New Garia

Mamata Banerjee during her first tenure as the railway minister initiated the project of Tollygunge – Garia metro extension. During her second tenure (2009–2011) she inaugurated the extension, and also introduced new Air Conditioned rakes, manufactured indigenously at the Integral Coach Factory.

The new extension to Garia Bazar in the south opened to the public on 23 August 2009. The Garia Bazar station was named after Kavi Nazrul. A final extension, in the southern end, from Kavi Nazrul (Garia Bazar) to Kavi Subhash (New Garia) was inaugurated on 7 October 2010, bringing the total number of stations to 23. On the same day, two Air-Conditioned rakes were also pressed into service.

Future extension

The plan to extend Line 1 in the north from Noapara to Dakshineswar (4.0 km) is under execution now. It will be met by the metro line from Barrackpore at Baranagar (12.5 km).[5] Trial runs for this stretch has started on 23rd December 2020, after delay due to COVID-19 pandemic and is stated to be opened by February 2021.[6]

The stations on this stretch will be:

  1. Baranagar
  2. Dakshineswar

Features

Technical features

A metro car is getting ready for the journey towards Kavi Subhas (New Garia) at Dum Dum

Metro construction is of a very complex nature requiring the application of several new technologies in the fields of civil, electrical, signaling and telecommunication engineering. Indian engineers backed by their own experience and supplemented by their studies abroad adopted advanced technologies in the following fields for the first time in India.

  • Cut and cover method of construction using diaphragm walls and sheet piles.
  • Use of extensive decking to keep the traffic flowing over the cut while construction is in progress underneath.
  • Shield tunneling using compressed air and airlocks.
  • Ballastless track using elastic fastenings, rubber pads, epoxy mortar and nylon inserts.
  • Air-conditioning and ventilation system for environmental control of stations and tunnels.
  • Third Rail current collection system for traction.
  • Underground substations with dry-type transformers and SF6 circuit breakers.
  • Tunnel-Train VHF-radio communication system.
  • Microprocessor-based train control and supervisory remote control system for substations.
  • Automatic ticket vending and checking system.

Salient features

Total route length 27.39 km (17.02 mi)
Stations 24 (15 underground, 2 on the surface and 7 elevated)
Gauge 1676 mm (5 ft 6 in), Indian Broad Gauge
Cars per train 8
Maximum permissible speed 55 km/h (34 mph)
Average speed 30–31 km/h (19 mph)
Voltage 750 V D.C.
Method of current collection Third Rail
Travel Time: Noapara to Kavi Subhash 54 minutes (approx.)
Headways Average 10 minutes
Total estimated cost of the project 18.25 billion (US$255.9 million) (approx.)
Environment control Forced ventilation with washed and cooled air in case of non-AC rakes and air conditioning in case of AC rakes

Rolling stock

The whole fleet is vestibuled. Carbodies and mechanical components were made by ICF with electrical components made by NGEF, Bangalore. The fleet is unique in that it is the only railroad equipment in India with end-mounted cab doors (except for some of the WAG-6 series locomotives).

ICF has specifically designed, manufactured and supplied these cars for the first underground railway system. The special features incorporated are:

  • Traction power supply through third rail current collection system.
  • Automatic door opening/closing and continuous monitoring of the transit.
  • Automatic Train Stop (ATS) system which will automatically apply the brakes in case of human failure.
  • Automatic train operation (ATO) with the driver acting as the train supervisor (optional).
  • A public address system is provided on the trains to announce approaching stations. A central dispatcher can contact any of the train crew and also make important announcements directly to passengers over the system.

With all these features, the design and manufacturing process of these cars to a very high standard of reliability and safety has been a challenge. This was achieved without any technical collaboration.

Reservation for women

In 2008, the Kolkata Metro Railway experimented with the practice of reserving two entire compartments for women.[7]

This system was found to be ineffective and caused inconvenience for a lot of commuters (including women) and the plan was eventually dropped by the metro authority. But a certain section of seats in each of the eight compartments is reserved for women.

Problems with this line

The coaches were manufactured by ICF with no air-conditioning Indian Railways signalling was adopted instead of European signalling.[8]

The founder of Delhi Metro, E. Sreedharan said Indian Railways are not experts at urban transport, and misplanned the Kolkata metro from the beginning.[8] A private company should run the metro and can bring it up to standard in five years.[8]

Since, Kolkata Metro is under Indian Railways, it can't take its own independent decisions. It has to rely on Indian Railways for everything (like rakes etc.). The rakes are ordered directly from ICF without floating any global tenders. And ICF being inexperienced in manufacturing metro rakes, has delivered faulty rakes. Thus causing snags and accidents.

See also

References

  1. "Kolkata Metro Map".
  2. "Kolkata Metro is now the 17th zone of Indian Railways". The Times of India. 29 December 2010. Retrieved 29 December 2010.
  3. https://www.telegraphindia.com/states/west-bengal/game-of-the-name/cid/1266496
  4. TNN. "Mamata paves way for Metro's northern journey". Times of India. Retrieved 12 October 2019.
  5. Express News Service (3 January 2010). "Mamata lays foundation for Dum Dum-Dakshineswar Metro". Express India. Retrieved 7 July 2012.
  6. Mondal, Biswadeep (23 December 2020). "Metrorail Kolkata conducts first trial run of Kolkata's Dakshineswar Metro". Mint.
  7. "Life in a ladies' Metro". www.telegraphindia.com. Retrieved 21 February 2020.
  8. "DMRC MD E Sreedharan says many Indian cities need metro rail urgently - Business Today". Businesstoday.intoday.in. 9 January 2012. Retrieved 7 July 2012.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.