The Narude Dam is a gravity dam on the Shō River about 22 km (14 mi) south of Nanto on the border of Toyama and Gifu Prefectures, Japan. It was constructed between 1950 and 1952. The dam has an associated 97 MW hydroelectric power station which was built in two parts. The first part of the power station (37 MW) was commissioned in 1951 and the second part of the power station (60 MW) was commissioned in 1975. Of the nine dams on the Shō River it is the sixth furthest downstream.[1]

Narude Dam
Downstream face
Location of Narude Dam in Japan
CountryJapan
LocationToyama/Gifu Prefecture
Coordinates36°21′00.31″N 136°52′29.72″E
PurposePower
StatusOperational
Construction began1950
Opening date1952
Owner(s)Kansai Electric Power Company
Dam and spillways
Type of damGravity
ImpoundsShō River
Height53.2 m (175 ft)
Length190 m (620 ft)
Dam volume103,000 m3 (135,000 cu yd)
Spillway typeCrest overflow, 8 tainter gates
Reservoir
Total capacity9,709,000 m3 (7,871 acre⋅ft)
Active capacity3,186,000 m3 (2,583 acre⋅ft)
Catchment area762.3 km2 (294.3 sq mi)
Surface area.62 km2 (0.24 sq mi)
Normal elevation391.6 m (1,285 ft)
Power Station
Operator(s)Kansai Electric Power Co., Inc.
Commission dateOriginal: 27 November 1951
New: 20 March 1975
Hydraulic headOriginal: 53 m (174 ft)
New: 52.95 m (173.7 ft)
TurbinesOriginal: 2 x 18.5 MW Francis-type
New: 1 x 60 MW Francis-type
Installed capacity97 MW