Nairobi Southern Bypass Highway

The Nairobi Southern Bypass Highway is a road in Kenya, forming a semi-circle through the south-western neighborhoods of the capital city of Nairobi. The road allows traffic from Mombasa, destined for western Kenya and Uganda to bypass downtown Nairobi, thereby reducing traffic congestion in the city's central business district.[1]

Nairobi Southern Bypass Highway
Route information
Length18.4 mi (29.6 km)
HistoryDesignated in June 2012
Completion in November 2016
Major junctions
Southeast endNairobi-Mombasa Road at Likoni Road
 Uhuru Gardens
Ngong Road
Muguga
Northwest endGitaru
Highway system
Roads in Kenya

Location

The road starts at the junction of the Nairobi–Mombasa Road and Likoni Road, approximately 10 kilometres (6 mi) south-east of the city centre.[2] The road then loops through the south-western suburbs of Nairobi, including the northern environs of Nairobi National Park, Uhuru Gardens, Lang'ata and Dagoretti. In Dagoretti, the road enters Kiambu County and then turns northwards, to pass through Muguga and end in the town of Kikuyu, in a suburb known as Gitaru. At that location, the road connects with the Nairobi-Malaba Road (A104).[3]

The total length of the Nairobi Southern Bypass Highway is approximately 29.6 kilometres (18 mi).[4]

Overview

This road is intended to relieve traffic congestion in the capital city's central business district, by diverting long-distance traffic from and to the port city to Mombasa, destined for western Kenya and the land-locked countries of Uganda, Rwanda, Burundi, South Sudan and the eastern parts of the Democratic Republic of the Congo.[5]

In a similar effort, other bypass highways have been built on the northern and eastern sides of Nairobi, with the objective of alleviating downtown traffic congestion.[6]

Construction

The Kenya National Highway Authority (KeNHA), selected China Road and Bridge Corporation to construct the four-lane dual carriageway highway, at a cost of US$180 million (KSh18 billion). The construction was funded by the government of Kenya together with the Export Import Bank of China, as illustrated in the table below.[5][7] The completed road was commissioned by the president of Kenya, Uhuru Kenyatta and his guest, the president of Tanzania, John Magufuli, on 2 November 2016.[8]


Funding for Nairobi Southern Bypass Highway
RankDevelopment PartnerContribution in US$PercentageNotes
1Exim Bank of China
153 million
85.0Loan
2Government of Kenya
27 million
15.0Investment
Total
180.0 million[8]
100.0

See also

References

  1. Kibet, Lonah (23 May 2013). "Smooth ride for motorists ahead as Southern by-pass works begin". The Standard (Kenya). Nairobi. Retrieved 5 March 2019.
  2. Globefeed.com (5 March 2019). "Distance between Central Nairobi, Kenya and DTB Centre, Kenya". Globefeed.com. Retrieved 5 March 2019.
  3. Google (5 March 2019). "Location of the Nairobi Southern Bypass Highway" (Map). Google Maps. Google. Retrieved 5 March 2019.
  4. Globefeed.com (5 March 2019). "Distance between DTB Centre Nairobi, Kenya and Gitaru, Kenya". Globefeed.com. Retrieved 5 March 2019.
  5. Patrick Thuita (18 August 2016). "Nairobi Southern Bypass now set for official opening". Nairobi: Constructionkenya.com. Retrieved 5 March 2019.
  6. Daily Nation News (8 February 2009). "Bypass construction starts without approval from environmental body". Daily Nation. Nairobi. Retrieved 5 March 2019.
  7. Antony Kiganda (27 June 2016). "Nairobi Southern bypass nearing completion". Nairobi: Construction Review Online. Retrieved 5 March 2019.
  8. Mathenge, Oliver (2 November 2016). "Presidents Uhuru and Magufuli open Southern Bypass to decongest city". The Star (Kenya). Nairobi. Retrieved 5 March 2019.

This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.