Malpasset Dam


The Malpasset Dam (French: Barrage de Malpasset) was an arch dam on the Reyran River, located approximately 7 kilometres (3.8 nmi; 4.3 mi) north of Fréjus on the French Riviera (Côte d'Azur), Southern France, in the Var department. It collapsed on 2 December 1959, killing 423 people in the resulting flood.[1][2] The damage amounted to an equivalent total of US$68 million. The event also ushered in the practise of posthumous marriage in France for civilians as many women who lost their fiancés were granted the right to marry them after death.

Malpasset Dam
The ruins of the dam 2014
Location of Malpasset Dam in France
Official nameFrench: Barrage de Malpasset
LocationFrance
Coordinates43°30′43.48″N 6°45′23.40″E
Construction beganApril 1952
Opening date1954
Demolition date2 December 1959
Construction cost580 million francs (by 1955 prices)
Designed byAndré Coyne
Owner(s)Département Var (59)
Dam and spillways
Type of damarch dam
ImpoundsReyran River
Height222 metres (243 yd)
Length66 metres (72 yd)
Width (crest)1.5 metres (1.6 yd)
Width (base)6.78 metres (7.41 yd)
Reservoir
Total capacity50 million cubic metres (65×10^6 cu yd)
Website
https://frejus-tourist-office.com/discover/barrage-de-malpasset/

Construction

The dam was a doubly curved equal angle arch type with variable radius. It was built to supply drinking and irrigation water for the region. Construction began in April 1952 and was finished in 1954. Another source reports that construction began as early as 1941. Delays due to lack of funding and labor strikes interrupted construction a few times. The project was led by well-known French engineer André Coyne. Construction cost 580 million francs (by 1955 prices), and was funded and owned by Var département. Concurrent with the dam construction, the A8 autoroute was also being built 1,400 m (1,500 yd; 0.76 nmi) further down the course of the Reyran from the dam location.

The dam was supposed to regulate the rate of the flow of the river that it was near and store 50 million cubic metres of water for agriculture, and domestic use and for the tourism sector of the area.[3] The dam was 222 metres in width, 66 metres high, and had a thickness of 6.78 metres at the base and 1.5 metres at the rim.[4]

Disaster

Malpasset Dam Breach
The breached Malpasset Dam
Native name French: Rupture du Barrage de Malpasset
DateDecember 2, 1959 (1959-12-02)
Time21:13 (CET)
Coordinates43°30′43.48″N 6°45′23.40″E
TypeDam failure
CauseExcess water level due to heavy rainfall
Deaths423
Non-fatal injuries83
Property damage425 million euros of 2010[5]
WebsiteArchived 2017-09-24 at the Wayback Machine

Signs of an imminent collapse began in November 1959: a "trickle of clear water observed high on the right [side]" and then cracks noticed later in the month in the concrete apron at the dam toe.[6]

The dam was breached at 21:13 on December 2, 1959.[7] The break was partially due to rainfall and thus the rising level of water; by noon on 2 December 1959 the reservoir had reached its maximum level. The guardian André Ferro asked for permission to release the excess water and was denied the ability to do so until 6pm of that day.[7] By then, the amount of water was so high that it took three hours to release only a few centimetres of water.[4] The entire wall then collapsed with only a few blocks remaining on the right bank. Pieces of the dam are still scattered throughout the area.

The breach created a massive dam-break wave, or wall of water, 40 m (44 yd; 130 ft) high and moving at 70 km/h (38 kn; 43 mph), destroying two small villages, Malpasset and Bozon, the highway construction site, and in 20 minutes, still standing 3 m (3.3 yd; 9.8 ft) high, reaching Fréjus. The water was recorded traveling at speeds up to 70 km/h (38 kn; 43 mph) with large chunks of the concrete wall some weighing up to 600 tonnes (590 long tons; 660 short tons).[4] Various small roads and railroad tracks were also destroyed, water flooding the western half of Fréjus and finally reaching the sea.

It was reported that the death toll of the dam breach was 423, with 135 children under the age of 15,[7] 15 minors between 15 and 21 years old, 134 men, 112 women, and 27 individuals who were never identified. Additionally, 79 children were orphaned[4] and 83 people were injured.[5] Other damage included 155 buildings destroyed, 796 buildings damaged, and 1,350 hectares (3,300 acres) destroyed, the amount of destruction totaling about 425 million euros in 2010 terms.[5]

Some 1959 postage stamps had a flood surcharge imprinted on them, to raise money for flood victims.

Cause

Geological and hydrological studies were conducted in 1946 and the dam location was considered suitable. Due to lack of proper funding, however, the geological study of the region was not thorough. The lithology underlying the dam is a metamorphic rock called gneiss. This rock type is known to be relatively impermeable, meaning that there is no significant groundwater flow within the rock unit, and it does not allow water to penetrate the ground. On the right side (looking down the river), was also rock, and a concrete wing wall was constructed to connect the wall to the ground.

A tectonic fault was later found as the most likely cause of the disaster. Other factors contributed as well; the water pressure was aimed diagonally towards the dam wall, and was not found initially. As a consequence, water collected under a wall and was unable to escape through the ground due to the impermeability of the gneiss rock underneath the dam.[8] Finally, another theory quotes a source stating that explosions during building of the highway might have caused shifting of the rock base of the dam. Weeks before the breach, some cracking noises were heard, but they were not examined. It is not clear when the cracking noises started. The right side of the dam had some leaks in November 1959.

Between November 19 and December 2, there was 50 centimetres (20 in) of rainfall, and 13 centimetres (5.1 in) in 24 hours before the breach. The water level in the dam was only 28 centimetres (11 in) away from the edge. Rain continued, and the dam guardian wanted to open the discharge valves, but the authorities refused, claiming the highway construction site was in danger of flooding. Five hours before the breach, at 18:00 hours, the water release valves were opened, but with a discharge rate of 40 m³/s, it was not enough to empty the reservoir in time.

Until the Malpasset incident, only four other incidents of arch-type dam breaches were recorded:

See also

References

  1. The Malpasset Catastrophe in 1959
  2. 1999 documentary in French with interviews and footage of the disaster
  3. French Ministry for Sustainable Development, DGPR/SRT/BARPI (April 2009). "Burst of a Dam, 2 December 1959, Malpasset (Var) France" (PDF). Analyse, Recherche et Information sur les Accidents: 1–7.
  4. "The Malpasset Dam Disaster – could the Var suffer again? – Riviera Reporter". www.rivierareporter.com. Retrieved 2018-04-23.
  5. Luino, Fabio; Trebò, Pier Giuseppe (January–April 2010). "The Malpasset dam (France) fifty years after the failure of December 2, 1959 and references to similar Italian cases". Geoingegneria Ambientale e Mineraria (in Italian). 47 (1): 53–80. ISSN 1121-9041.
  6. Goodman, Richard E (May 16, 2013). "On the Failure of Malpasset Dam" (PDF). University Cal. Berkeley PowerPoints.
  7. "60 ans après la catastrophe - A Fréjus, les 423 morts du Malpasset hantent toujours les survivants". www.lamontagne.fr. 22 November 2019. Retrieved 22 November 2019.
  8. Erpicum, S; Archambeau (2004). "Computation of the Malpasset Dam Break with a 2D Conservative Flow Solver on a Multiblock Structured Grid" (PDF). International Conference on Hydroinformatics; World Scientific Publishing Company: 1–8.
  • J. Bellier, Le barrage de Malpasset, 1967