The Wey barge was based on the earlier West Country barge designs and the first barges built specifically for use on the Wey were probably built at Honeystreet Wharf, near Devizes. The earliest that this could be was 1810 as the Kennet and Avon Canal was opened through to the Thames that year.

Wey barge Perseverence IV moored at Dapdune Wharf

Barge building

There is little evidence of barge building on the Wey before 1876. Many of the barges used before then were constructed at the Honeystreet Wharf near Devizes. The Kennet and Avon Canal opened in 1810 which allowed the passage of barges to enter the Thames and thus the Wey. The first barges from here to be used on the Wey were known as "West Country" or "Western" barges[1] which were designed to be used on the western waterways such as the Kennet and Avon Canal and the Thames and Severn Canal. These became the standard for the Wey Navigation.

Around 1876 the Edwards family moved from Honeystreet to Dapdune Wharf setting up a barge building business. The Surrey Advertiser published an article in 1909 on the launch of the barge Dapdune[2] built by George Edwards and his three sons.

Types of barges

The main method of propulsion on the navigation was by horse. Barges were rowed, sailed or towed by larger vessels from the various London quays to Thames Lock at Weybridge where they were 'horsed up' for a price of 9/6d.:[3] The sizes of these barges were determined by the size of the locks they needed to travel through. These were[1]

Lock sizes
CanalLengthWidth
River Wey and Navigation73 ft 6 in (22.40 m)13 ft 10.5 in (4.229 m)
Basingstoke Canal72 ft 6 in (22.10 m)13 ft 6 in (4.11 m)
Wey and Arun Canal74 ft 9 in (22.78 m)13 ft 0 in (3.96 m)

Construction

Typical Wey barge design

The barges were generally a flat structure with a small cabin at the stern and a locker in the bows for stowing ropes and other equipment. The cargo hold was covered by either wooden hatches or a canvas tarpaulin which were held above the cargo by the hatch beam.

The ribs of the hull were built from oak. There was a steam chest behind the shed where the wood could be shaped. However the Edwards family preferred to find wood naturally shaped.

The hull was planked with pitch pine. Pitch pine was used because it was lightweight and came in long lengths so required less joints. Elm was tried, and although it was more water resistant, it was heavier and therefore the barge had a lower cargo capacity. The gaps between the planks were sealed by caulking, a process involving mixing a fibrous substance, often unpicked old rope, with tar and ramming the mixture into the joints while the tar was hot.

The barge was flat bottomed and straight sided, this meant that it could operate in shallow water with a reasonable cargo, also it could be safely grounded in tidal waters. Once the hull was complete it was covered in pitch to create a watertight finish. The barge was built on trestles to keep it off the ground and assist in launching. Only the hull was built in the shed. On completion the water side of the shed was removed and the barge was launched sideways into the river. The barge was then towed up to the area where the pleasure boats are moored today and it was here that fitting out was completed. This was also the area used to repair barges.

The Wey barge was 73 ft 6 in (22.40 m) in length and the width was constrained by the narrowest lock to 13 ft 10.5 in (4.229 m).[4] A barge would have only inches to spare when going through the lock. They could carry 80 tonnes of cargo from the Thames to Coxes mill. From Coxes going upstream the capacity was reduced to 50 tonnes as far as Guildford and further reduced for the journey to Godalming owing to the decrease in the depth of water available.

Barges of the Wey Navigations

Over time there have been many barges, each with its own name. Names were reused, such as Perseverance which has been used on four different barges.

NameDateBuiltRegisteredNumberNotes
Arun1846Recorded in Stevens Barge Master Accounts[5]
Reliance1847Recorded in Stevens Barge Master Accounts[5]
1885Recorded in Stevens Barge Master Accounts[6]
Perseverence1877Recorded in Stevens Barge Master Accounts[6]
Industry1880Complaint letter about 'Captain Cox worse for drink'[7]
1880Recorded in Stevens Barge Master Accounts[6]
Providence1907Insurance Premium[8]
1880Recorded in Stevens Barge Master Accounts[6]
Diligent1907Insurance Premium[8]
1885Recorded in Stevens Barge Master Accounts[6]
Hope1885Recorded in Stevens Barge Master Accounts[6]
Wey1907Insurance Premium[8]
1895Recorded in Stevens Barge Master Accounts[6]
Alert1907Insurance Premium[8]
1895Recorded in Stevens Barge Master Accounts[6]
Surrey1907Insurance Premium[8]
Unity1907Insurance Premium[8]
Dapdune1909190931/03/19108848Built Dapdune Wharf, Launched,[2] last used Oct-1940
Industry (II or later)191319135/12/19138833Built Dapdune Wharf, Last Used Nov-1946
Providence (II or later)191419148830Built Dapdune Wharf
Wey (II or later)1914191418/10/19158843Built Dapdune Wharf, Last used May-1951
Kate191519154/04/19178848Built Dapdune Wharf
Victory1920192018/10/19138840Built Dapdune Wharf, Last used Nov-1956
Renown192319238/03/19248812Built Dapdune Wharf, Last used Jun-1956
Speedwell1924192419/10/192513298Built Dapdune Wharf, Last used Jun-1969
Hope (II or later)1929192906/09/19295507Built Dapdune Wharf, Last used Jan-1969
Reliance (II or Later)1931193125/07/193214652Built Dapdune Wharf[9]
Perseverance IV1934193404/06/193715639Built Dapdune Wharf, Last used Jun-1969

Usage

The Wey and Godalming Navigations was a major distribution route for the distribution of goods in south England and along with the Wey and Arun Canal it provided an inland route from London to the South Coast. The goods transported varied from gunpowder from the Gunpowder Mills at Chilworth[10] to more usual raw materials such as timber, coal, grain and wool. The amount of goods that could be carried was governed by the size of the barges used which were restricted by the size of the locks in the various waterways. As each waterway was constructed and owned by a different company the size of the locks varied.

References

  1. Griffiths, D.D.G (1965). Dissertation on the Wey Navigation and it's Barges. National Trust Dapdune Wharf: Loughborough Training College. pp. 184, 188, 189.
  2. "Launch of New Barge". Surrey Advertiser. 1909.
  3. "Wey Navigation Records". G129. 91. 1849–1870.
  4. McKnight, Hugh (1975). Shell Book of Inland Waterways. Newton Abbot: David and Charles. p. 441.
  5. Stevens, William (1845–1860). "Bargemaster Accounts". G129/5/5.
  6. Stevens, William (1877–1900). "Bargemaster Accounts". G129/5/8.
  7. Cox. "Godalming Papers - Complaint Letter". G137/12/32.
  8. "Godalming Papers". G137/12/32.
  9. Wardle, Alan (1992). Barge Building on the Wey.
  10. "Chilworth Gunpowder Mills in the Great War". Surrey in the Great War. Retrieved 16 January 2019.
This article is issued from Wikipedia. The text is licensed under Creative Commons - Attribution - Sharealike. Additional terms may apply for the media files.